USAC Links
Schedule
- : Posting Start Date
- : Last Date for Submission of Vendor Questions
- : All Vendor Questions Answered and Posted
- : 5pm Proposal Deadline
- : Proposal Analysis Commences
Questions & Answers
- Question: I see no mention of routers, managed or otherwise. Should we put routers in our bid? Otherwise it will just be a handoff to your network.
Answer: In order to provide as much flexability for vendors as possible we include Network Equipment on the form 461. If equipment isn't required for your solution please disregard. - Question: I don’t see Park Hills HCP#. I see it on your network diagram but not on the sites and services matrix. Are we quoting that site and is it part of the network.
Answer: Yes, please provide pricing for Park Hills as well, it is part of the network.